University of Antwerp ready for the future thanks to major renovation project

For the first phase of the renovation of the University of Antwerp’s buildings on Paardenmarkt (formerly IHAM and Hogeschool Antwerpen), engineering consultancy BOTEC was commissioned, in collaboration with DMT Architecten and Bureau Bouwtechniek, to convert existing rooms into computer rooms for around 300 students. Following the opening of the computer rooms in January 2020, the second phase will begin. This involves the renovation and restoration of the existing buildings to accommodate the Product Development programme..
Due to a general shortage of computer rooms at UA, the new rooms will be brought into use before the second phase begins and will be occupied almost continuously.
However, this gave rise to two problems that had to be resolved in advance. Access to these computer rooms during the second-phase works was crucial. The current entrance will be within the construction site during the second phase. A new opening was therefore created into the adjacent existing Building R.
In addition, the existing toilet block in the courtyard will be removed during the second phase. To compensate, space was made on each floor of the adjacent Building E for new toilet facilities.

Computer room in the final stages of finishing.
Climate control
To ensure a healthy indoor climate in the new rooms, a type D ventilation system was chosen. In consultation with BOTEC and on its recommendation, the client made a very deliberate decision to provide the computer rooms with the necessary ventilation.
This is essential particularly in rooms of this kind, as equipment such as computers and printers produce dry, dusty air.
Ventilation in each room is controlled according to demand, based on measured CO2 levels and temperature. Air is supplied through a centrally suspended textile duct.
Following a thorough preliminary study and cost-benefit analysis by BOTEC, two air-to-water heat pumps were selected. These will compensate for heat losses caused by ventilation during the winter months and cool the air during the summer months.
Given the number of people present, the orientation and the heat sources in the rooms, providing peak cooling was strongly recommended. The rooms will also be used in July and August, making the choice to install cooling even more justified.
Data, lighting, access control and CCTV system
Fitting out computer rooms naturally requires attention to the huge volume of data cabling. The existing decentralised arrangement of data racks in the basement of Building D was inadequate. In addition, the existing racks had to be removed to make way for the new bicycle storage facility being built in phase 2. To centralise all new and existing data points, a new data room was created on the fourth floor, serving as the central point for Buildings D and E. All new and existing data points are fed from here.
As part of the energy-saving measures, all rooms were fitted with the latest generation of LED lighting, with daylight-dependent control based on measurements of the incoming daylight in each room.
All rooms are also fitted with an access control and CCTV system, which is fully managed by the client.
With repeat screens, central control of the speakers and full Wi-Fi coverage, these computer rooms are fully ready for the future.
Question about this story? Ask your question
Who worked on it
Universiteit Antwerpen Paardenmarkt in Antwerpen, renovation
- clientUniversiteit Antwerpen
- engineering consultancyIngenieursbureau BOTEC
- architectDMT Architecten
Keep following this
Get an email when a new story is published. No account needed.
- ProjectUniversiteit Antwerpen Paardenmarkt
- SubjectProjects
- CompanyUniversiteit Antwerpen
- CompanyIngenieursbureau BOTEC
- CompanyDMT Architecten