Exceptional construction site at the Kleine-Brogel air base

Work is currently under way on a remarkable project in Kleine-Brogel, Limburg, both in terms of the size of the site and the complexity of the work. A concrete surface covering no less than 30,000 m² is being laid beside the main runway for the cargo parking and loading and unloading area. APK Wegenbouw was selected to carry out the work. To ensure effective drainage, it once again chose to work with Deschacht.
Project manager and specification author Bart Geerts explains: “The water management involved in this project sounds deceptively simple: retention, settlement and discharge. However, the site presents a number of specific challenges, which is why the services of, among others, Deschacht’s design department were called upon. The scale of the work was one such challenge. The entire paved area is surrounded by drainage channels. These channels also had to be connected to an underground retention and settlement basin. An open basin would attract birds, which would obviously pose a risk to the aircraft’s jet engines. Thirdly, the markings are crucial for receiving aircraft safely. The surface was laid in concrete rather than asphalt because of its resistance to the aircraft’s point loads. A perfect installation is therefore essential.”

‘Excellent value for money’
APK Wegenbouw, which specialises in infrastructure works for water mains and installations, energy networks, telecoms networks and road construction, specified the materials for the project. Site manager Koen Brebels explains: “We did indeed choose to work with Deschacht again. The products they offer represent excellent value for money, and the working relationship is very pleasant. The need for both an optimal plan and high-quality materials for this project became clear when heavy downpours left the entire site under water in June 2021. The paving had not even been laid yet.”
A total of 411 m of Faserfix Super 300 01 (Hauraton) drainage channels were installed, including KL F-900 cast iron grates (Collinet). Koen Brebels praises the dimensional accuracy of the Faserfix channels. “Although we had to work with concrete, we achieved a perfectly straight line with the channels: everything fitted together neatly. The result speaks for itself, thanks in no small part to all the installers.”
Water flows through these channels to an underground settlement basin via a double-walled HSKPEA090 oil separator (Collinet). Deschacht supplied 3,600 IT Plus Variobox SP units for this purpose. The system is specifically designed for use in large-scale applications. Variobox contributes to this sustainable water management system by infiltrating excess water.
The drainage system is complete, and the entire project was handed over at the end of April 2022.
Een zakelijke vraag aan Deschacht? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectProjects
- CompanyDeschacht