More than 2,000 kilometres of cable for AZ Delta

The new AZ Delta hospital in Roeselare opened its doors in March. A prestigious project, also for Cebeo. With more than 2,000 kilometres (!) of cable delivered on schedule, Cebeo played a crucial role in ensuring the electrical works ran smoothly. EEG, Electro Entreprise Gullegem, knew it could not have chosen a better partner than Cebeo for the job.
A faulty water pipe during the final phase of the works briefly delayed the ceremonial opening of the new AZ Delta. But the doors officially opened last month after all. Large-scale projects like this can be delayed for all sorts of reasons. That is why the timely delivery of materials is so important. Any delay can trigger a domino effect.

Cebeo has a huge central cable stock, both in terms of volume and range.
Huge cable volumes
This kind of logistical operation is one of Cebeo’s strengths. “We have been working with Cebeo for many years,” says Joost Verschuere, Project Leader at EEG. “We were responsible for all the works, from high and low voltage to CCTV and access control. That meant all the cabling, too. We knew Cebeo could meet our needs for the cabling: on-time deliveries and huge volumes. What else would you call volumes of 1,200 kilometres of data cable and 40 kilometres of fibre-optic cable?”
Ensuring continuity
Rik Desmet, Key Account Manager at Cebeo: “EEG also called on Cebeo for motion detectors, patch cabinets, data centres and all the switchgear. We delivered the first batch of cable in April 2017. After that, everything was delivered at the planned times, on a call-off order basis. This ensured continuity of the works, without large volumes having to sit unused on site for too long. A project lasting two and a half years can only run smoothly if there are clear agreements and they are honoured.”
“Another challenge,” Rik Desmet continues, “was making as many connections as possible in a limited space. But Cebeo was able to provide a solution for that too, with the right materials.”

The new AZ Delta hospital in Roeselare opened its doors in March.
From Roeselare to Kiev
Finally, Cebeo has a huge central cable stock, both in terms of volume and range. But extra preparations were made for this project, with several large quantities added to stock. The total? 2,320 kilometres of cable. That is equivalent to the distance from Roeselare to Kiev!
Cable: staggering figures!
- 40 km of fibre-optic cable
- 1,200 km of data cable
- 130 km of earthing wire
- 690 km of power cable
- 180 km of fire-resistant cable
- 80 km of control cable
AZ Delta in 5 figures
- 115,000 m²
- 700 beds for longer stays
- 110 day hospital beds
- 2,500 employees
- Cost: 425 million euros
Een zakelijke vraag aan Cebeo? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectAZ Delta
- SubjectProjects
- CompanyCebeo