The port of Zeebrugge has gained a new logistics site. Intervest Offices & Warehouses invested in a state-of-the-art platform for importing goods into Europe in containers, and vice versa. Work began in 2021, and the project was completed a year later. The result is a 76,000 m² logistics park that guarantees an optimal indoor climate thanks to Daikin’s energy-efficient products.
Divided into ten warehouses, each with ten loading bays and ready-to-use office facilities, the site is one of the largest logistics projects in West Flanders. In addition to the warehouses, it includes a 22,000 m² container storage area, a head office, parking for 200 cars, and a waiting and drop-off zone for lorries. With this investment, Intervest aims to attract and accommodate Chinese and international logistics operators importing goods into Europe in containers from around the world, and vice versa. The initial focus is on e-commerce, automotive and food.
Complete HVAC solution for optimum comfort
For an industrial space like this, combining offices and warehouses, the challenge was to find the right heating and cooling solution for the different types of space. Daikin’s complete solutions ensure an optimal indoor climate. The head office and offices in the halls are equipped with a VRV heat recovery system and associated indoor units. The warehouses, with a combined total area of around 7,000 m², are heated and cooled by ten central air-to-water heat pumps, each with a capacity of 400 kW.
“Installing the heat pumps on the roof was a major undertaking with a tight schedule. We also laid no less than three kilometres of pipework so that every hall could be equipped with the necessary air heaters,” says Thomas Claeren, Managing Director of Develtere.
A productive working environment guaranteed
The Daikin VRV system with heat recovery was chosen throughout the office spaces. Keeping the indoor temperature at the optimum level is important for maximising employee comfort. Individually adjustable concealed units make it possible to heat and cool the spaces all year round.
In the warehouses, it is especially important to maintain a constant temperature in winter. Given the high output required, a central air-to-water system is the only suitable solution. Heat pumps are therefore used in combination with air heaters.
“Given the size of the warehouses, we had to think carefully about which system to use. The capacity required for each hall is so considerable that we ultimately opted for air-to-water heat pump solutions. The right temperature is maintained, as are indoor air quality and working comfort. The project is also BREEAM-certified with an Excellent rating, which is a significant added benefit,” says Frank Devenyn (engineering consultancy Ingenium).
Efficient control via I-Touch Manager
Given the size of the entire building, it makes sense to manage it from a central location. The owner chose Daikin’s Intelligent Touch Manager, which brings all the climate control units together in one system. The interface enables the building to be managed energy-efficiently. It shows which unit or zone consumes the most energy, allowing action to be taken to reduce consumption and prevent energy waste. This is a major advantage for an industrial site like this.
Close collaboration ensures rapid installation
The biggest challenge on this project was the schedule. The entire project had to be completed within a year, which meant tight deadlines for installing the heating solutions. Good communication between the manufacturer, installer and engineering consultancy was essential. Which system should be chosen, and how could it be installed as efficiently as possible? The VRV system is a cost-effective solution that makes installation easier, as do the central air-to-water heat pumps in the warehouses. The result is an optimised system with a straightforward design that meets the customer’s requirements.
“To speed up the installation considerably, we chose to fit the circulation pump and buffer tank to the heat pumps in advance at our Daikin factory. For each hall, the installer prepared a frame in the workshop, with the necessary fittings, such as filters and valves, already installed. This helped ensure that the heat pumps could be installed more quickly,” concludes Kris Mertens, Product Manager at Daikin.
Daikin’s complete HVAC solution at a glance:
- Fossil-free, climate-neutral solution
- 10 air-to-water heat pumps, each with a capacity of 400 kW, for climate control in the halls
- VRV with heat recovery for the head office
- Simultaneous heating and cooling in the offices with heat recovery
- All heat pumps used operate with the low-GWP refrigerant R32
- Central control via Cloud controller
A business question for Daikin Europe? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- SubjectNews
- CompanyDaikin Europe