Fire safety begins long before smoke or flames appear

In this podcast, Vincent Vancaeyzeele of Techlink talks to Bert Van Vaerenbergh of Etex/Promat and Bart Tastenoye of Spelsberg about fire protection in buildings and building services installations. Topics include compartmentation, fire-resistant service penetrations, maintaining the function of electrical installations, regulations, renovation, BIM and the role of installers in ensuring correct installation. They also discuss the challenges in tunnels, high-rise buildings, data centres and existing buildings. One question is central: how do you ensure that building services and installations continue to do what they are supposed to do in the event of a fire?
Speakers:
- Bert Van Vaerenbergh: Etex
- Bart Tastenoye: Spelsberg
Host: Vincent Vancaeyzeele (Techlink)


Een zakelijke vraag aan Spelsberg Belgium? Get in touch
Full transcript
Alle hoofdstukken (36)
- Fire protection and Promat’s role
- Developments in service penetrations and fire testing
- Maintaining the function of electrical installations
- Fire safety and evacuation in tunnels
- Specific requirements for tunnels and high-rise buildings
- The Grand renovation project in Nieuwpoort
- Sharing knowledge with installers
- Where maintaining circuit integrity goes wrong in practice
- Account for function retention during the design stage
- How materials behave in a fire
- Risk assessment and the Promat Selector
- Who is responsible for what?
- The difference between the plans and the finished work
- Sizing walls, ceilings and support structures in advance
- Changing regulations and technical feasibility
- Requirements also need to be achievable
- Fire safety in renovations where space is limited
- Inspection, handover and documentation
- Regulations versus practice
- Specifications, inspectors and collaboration
- Regulations, the fire service and specialisation
- New technologies and the role of the fire service
- Innovations in fire detection and extinguishing systems
- Data centres, AI and automatic fire detection
- Compartmentation and renovation of existing buildings
- Fire safety in the existing building stock
- Bringing older buildings up to current standards
- New building systems and new fire tests
- BIM and digitalisation on site
- BIM among manufacturers and installers
- Ask for advice to prevent mistakes
- Cooperation between different installers
- Additional cabling and load capacity
- Coordination within construction teams
- Specialisation and choosing the right partner
- Closing remarks
Fire protection and Promat’s role
Vincent Vancaeyzeele Welcome, everyone, and welcome to our listeners. Today we’re at Louwers Mediagroep in Oostkamp. In this podcast, we’ll be talking about fire protection. It’s a hugely exciting subject for installers. What happens when things go wrong? You won’t just have to listen to me today. I have two fascinating guests with me, Bart and Bert, who will guide us through the discussion. And Bart Tastenoye of Spelsberg. Perhaps we’ll start with you, Bert. Could you introduce yourself, explain exactly what you do at Promat and tell us what solutions you offer the market?
Bert Van Vaerenbergh Yes, thank you. Good morning, Vincent and Bart. I work for Etex, the Belgian Etex company, specifically for Promat. We provide fire protection solutions for the construction industry, across three segments. The first is structural fire protection. It’s very important for a building to retain its structural integrity, so that in the event of a fire, occupants can move through the building and evacuate. We offer solutions for that. The second segment is compartmentation, to keep certain areas of a building safe from fire for longer. The third concerns services that pass through compartmentation barriers. Electrical and other building services inevitably have to pass through them, so it’s essential that the compartmentation remains intact. We also provide the right solutions for service penetrations.
Developments in service penetrations and fire testing
Vincent Vancaeyzeele Where have you seen the most progress in recent years?
Bert Van Vaerenbergh I think it’s fair to say that service penetrations through compartmentation barriers have evolved. Their importance is now generally recognised, or at least understood by specifiers, clients and installers. That’s why we carry out a great deal of fire testing. We have our own furnaces and conduct several fire tests each year on new systems, new compartment walls and new types of walls, ceilings and so on. We’re also investing in digital technologies to find the right solutions. There has been progress in recent years.
Read the full transcriptCollapse transcriptnog 34 hoofdstukken
Maintaining the function of electrical installations
Vincent Vancaeyzeele Fascinating, thanks, Bert. Bart, what exactly do you run through a building and through those wall penetrations?
Bart Tastenoye First, let me introduce myself. I’m Bart Tastenoye from Spelsberg Belgium. I’ve been working with fire-resistant installations for a number of years. My colleague here is concerned with the building itself. My focus is on ensuring that electrically connected building services continue to function during an evacuation, as he just explained, so that people can get out and extraction systems, sprinkler systems and whatever else is needed can keep working. Signage too, of course.
Fire safety and evacuation in tunnels
Vincent Vancaeyzeele Can you give us an example of a typical building where fire safety is a major concern?
Bart Tastenoye We often work in tunnels. They’re not buildings, but installations where the length of the tunnel affects how easy or difficult it is to evacuate. What lies above the tunnels also affects how far apart the escape routes are, and so on. Obviously, if a fire breaks out in a tunnel, it’s vital that the systems, evacuation systems and so on, remain operational and help people find their way to the exits. Ideally, they should be able to do so safely, without inhaling smoke or other chemical substances. All these factors have to be taken into account in the installations. We have to consider several parameters. It’s not just a matter of ensuring that everything remains attached to the walls or ceilings as specified in the evacuation plan. The type of product used must also be free of issues relating to its ingredients or chemical composition. Thirdly, of course, it has to remain functional. The clamps and other components used to connect everything must also remain fully functional for 90 minutes, or for whatever other period is specified in the contract documents.
Specific requirements for tunnels and high-rise buildings
Vincent Vancaeyzeele Bert, you mentioned tunnels. When I drive through Brussels, I look around and see all sorts of things hanging from the ceilings, as well as openings here and there into the adjacent tunnel. Structurally, those ceilings must not collapse. In Brussels, it’s hard enough to keep them up even without a fire. I can imagine that a fire makes things even more challenging.
Bert Van Vaerenbergh Yes, indeed. Of course, we shouldn’t forget that a tunnel is a specific environment with special requirements. Fire tests must also be carried out to specific fire standards designed specifically for tunnel solutions. These can cover everything from the lining, the tunnel walls’ aesthetic finish, to protecting the material behind that lining. Ceilings are much the same, and we offer solutions for those too. The same applies to service penetrations through compartmentation barriers. We offer solutions for these as well. And in new-build projects, particularly mid-rise and high-rise buildings, it’s hard to think of a project where this issue doesn’t arise.
The Grand renovation project in Nieuwpoort
Bert Van Vaerenbergh One example is the renovation of The Grand in Nieuwpoort, an old hotel being restored to its former glory. It will have about 100 rooms. We provided solutions for structural fire protection and compartment walls, such as the walls between two apartments, which have to meet specific requirements. EI60, for example. Acoustics are also a consideration. Services, both electrical and plumbing, have to pass through these walls, and the penetrations must comply with the relevant guidelines. This is a large project, and fire safety was considered from the outset. The locations of the service penetrations and the solutions to be used were identified early on. The project is now nearing completion, and the building services installers are busy putting in the appropriate fire-stopping systems, with some coordination and oversight from us.
Sharing knowledge with installers
Vincent Vancaeyzeele Looking at the installer market, we as a trade federation receive a lot of questions about what is and isn’t allowed, both in terms of applications and which materials can or can’t be used. What’s happening to the level of knowledge across the broad installation market? There are professional contractors, but also installers who have to carry out additional work. Is knowledge improving or declining, and what are you doing to raise the level?
Bert Van Vaerenbergh A key priority is indeed passing on knowledge to installation companies. That’s relatively straightforward on larger projects, because the services or penetrations are installed by specialist building services companies, which also have… We find that some penetrations are installed by smaller contractors, by the teams putting up the walls. They can also install certain types of penetration. Training and knowledge-sharing are especially important in those cases, and we’re working on that too. For several years now, we’ve been organising roadshows where we teach and show technicians how to install service penetrations, and where each type should be installed. We’re working to catch up, and I think we’re already seeing results.
Where maintaining circuit integrity goes wrong in practice
Vincent Vancaeyzeele Bart, two questions for you about Spelsberg. Where do things often go wrong? And what understanding needs to be more widespread in the market so people can assess in advance: ‘Should I do this, or is it better not to?’
Bart Tastenoye More and more buildings now require systems to maintain their function during a fire, which makes sense. The more people who can be evacuated safely in a short time, the more likely it is that systems will need to remain operational. So there are more and more sites where this is required. At larger companies, teams, project managers and so on often have the necessary knowledge and carry it forward to subsequent projects involving function retention. In my view, the bigger the company, the better things generally are. On the other hand, as my colleague said, smaller companies often know less about it. They really don’t know how to approach it. Sometimes they’ve underestimated it slightly when costing the job and put all sorts of things down in the estimate. Then they reach the installation stage, and the questions start.
Account for function retention during the design stage
Bart Tastenoye We hope the project is still at a stage where changes can be made without too much disruption. In my view, one of the biggest mistakes is that, from the outset, the installation is laid out without taking account of the sections where function retention is required, perhaps because it hasn’t been considered necessary at that point. That can make it difficult to put things right in those areas later. This mainly concerns cabling and cable supports. I have less direct involvement with wall penetrations and the like. But if you trace a cable route that needs to maintain its function throughout, it has to remain operational along its entire length, including during a fire.
Bart Tastenoye For smaller contractors, I would offer this tip. When you are on site, you know the surroundings because you have been there to see how the project is going to be carried out. You should then look at the same situation through a different lens: what would happen here in a fire? Naturally, you can see what is mounted on the walls, but you also need to consider what the fire would do to the things we hang or install here, and so on.
How materials behave in a fire
Bart Tastenoye If there is metal involved, you know that the cables and the supports for the support structures will heat up and soften. As a result, they will sag. Then they will come down under their own weight. That needs to be taken into account, and it is better to do so during the preparation stage than to have to make changes later on. You may have forgotten that two other services are installed above them, and they may not be fire-resistant at that point. Adding extra weight above them, either when hanging your services or when they fall, means that, of course, they will no longer maintain their function.
Bart Tastenoye If you put yourself in a situation where there is an actual fire, you can see what happens to plastics, for example, including the cable boxes and junction boxes that we make at Spelsberg. They actually have a complete metal structure. There is a reason for that: the plastic will be gone after just a few minutes of fire. Even with the plastic casing, you need to consider what will be left. The metal supports will remain, along with the clamps inside them. They need to be designed or positioned so that, in the event of a fire, they are correctly sized for the load and weight, which will then exert a real downward pull, with as little negative impact as possible.
Risk assessment and the Promat Selector
Vincent Vancaeyzeele How do you assess a situation? How should I carry out a risk assessment? Bert, when you go to site, what are the first things you look at?
Bert Van Vaerenbergh First of all, we need to know what the fire-safety requirements are. They are usually set out in the specification. What location is involved, and what requirements apply? Then we can look for solutions. That is naturally the first step towards finding the right solution. For example, our Promat Selector is a digital tool on our website. Installers or specifiers can use it by entering a number of parameters to find the right solution. The system then provides them with installation guidelines. They can apply those to the situation in question. We can point them in a certain direction or suggest a particular installation method, but ultimately it is up to the client, architect or inspection body to confirm that it is correctly applied in that situation.
Who is responsible for what?
Vincent Vancaeyzeele I hear you mention the Selector, where you can make certain choices. Who should have done this? Was it the architect, discussing with the client what they wanted to achieve with the building? Was it the person drawing up the specification? Was it the engineering consultancy, which has to develop the design? Or is it the installer, who has to interpret the specification? Sometimes it is unclear who exactly has to determine what goes where, so that the right choices can be made about what ultimately needs to be installed in the building.
Bert Van Vaerenbergh Yes, on larger projects that is usually defined by the architect. The plans show where each penetration needs to be. The right techniques and penetration sealing systems then need to be used to seal them correctly in the event of a fire. Choosing the right system is, of course, down to the installer. There are several tested systems on the market, and the installer has to identify, select and apply the right one. On smaller projects, where an architect is not always involved, it is naturally the responsibility of the owner or even the contractor to ensure that the right seal is installed wherever a service passes through. So it depends somewhat on the size of the building, but I think several parties in the construction process need to take responsibility.
The difference between the plans and the finished work
Vincent Vancaeyzeele Let me come back to that, Bart. I just want to add briefly: everything looks fine on the plans, but in reality there is that pipe that has to go right there, making the wall penetration impossible or restricting it. How do you deal with that?
Bart Tastenoye Well, it is up to all the parties we have just heard from to deal with this, including the client. The client will sit down with the architects to assign a safety classification to parts of the building, for example, requiring them to remain accessible for a certain period or to be evacuated as quickly as possible. That means you end up with certain parts of the building where function must be maintained and compartmentation is also important, because there should, of course, be no fire where people need to pass through.
Sizing walls, ceilings and support structures in advance
Bart Tastenoye How should they be protected? Sometimes that means thicker walls. That also means you have to deal with cable penetrations very differently. Sometimes ceiling heights are an issue, because services still need to be installed there, and because the cable support systems need to be more robust. It also depends on the type of ceiling available to support the heavier structures. In most cases, these need to be oversized to minimise sagging in a fire, as I said earlier about metal. This means that all these factors should ideally be taken into account before the plans are drawn up.
Changing regulations and technical feasibility
Bart Tastenoye I remember a building caught between a change from old to newer regulations, which suddenly introduced different requirements. It was a hospital at the time. The installer had a very difficult time because the engineering consultancy did not even require compliance with the new regulations. The plans had been drawn up under the old regulations, and the architect had completed all the drawings. The ceiling heights in some parts of the building meant that function had to be maintained in other ways. That was not straightforward, because you end up looking for solutions that are not ideal. You always have to find a kind of middle ground between safety, or an adequate level of safety, and technical feasibility.
Requirements also need to be achievable
Bart Tastenoye Almost impossible to carry out. Just because an engineering consultancy specifies certain installation methods or certain types of cable, say, a 70 mm2 fire-resistant cable, that does not mean the installation is feasible. Those products exist, that is not the issue, but you need to be able to connect them to something. The cable is available, but are there clamps that can handle it? If not, there is no junction box for connecting a cable of that size either. These are small details, but they matter to the installer when it comes to interpreting the specification and actually carrying out the work. There are also the extra costs that often arise. Take my example of the 70 mm2 cable that needs to be connected. You might use a standard junction box for a cable of that size and wrap it in certain materials. But then it is completely enclosed, which means something still has to be done to it afterwards. Tough luck. We have to dismantle it all and rebuild it, which costs a great deal of money. So it is better to think everything through early in the design process than to look for solutions too late.
Fire safety in renovations where space is limited
Vincent Vancaeyzeele Renovation projects, for example, can leave you wondering what on earth to do. In apartment buildings with a shared services shaft, the CLV system for the gas boilers needs to be modified. That is a challenge. There is 15 years of history to contend with, so space has become very limited. Bert, how do you support people in dealing with this?
Bert Van Vaerenbergh We get enquiries about this every day. It is part of our job. In many cases, our advice is based on fire tests that have been carried out and for which an official classification report is available. But in many situations, we have to combine and interpret several fire tests to arrive at a recommendation. In some cases, the client, contractor or architect then has to agree to it. They do not always agree. This is especially true on renovation projects, where, as you just said, space is limited. Sometimes a compromise is needed, with the fire service or Buildwise, for example, also advising on a practical solution that can be implemented.
Inspection, handover and documentation
Vincent Vancaeyzeele People from Buildwise are often involved, and they play an important role in relation to insurance, handover and ultimately safety. I often hear that they come across situations where they make two observations. First, you can only assess what you can see. Second, buildings are empty at the start, but later they are full. How feasible is it to achieve theoretical safety or meet the theoretical requirements? What is your view?
Bert Van Vaerenbergh A building is handed over, and only then can people move in or users take up occupancy. So it is a turning point: the installed work has to be approved. On larger projects, this inspection is carried out by an inspection body, an officially appointed organisation that has to approve what has been installed. On smaller projects, there is usually no inspection body appointed, so it is up to the contractor to demonstrate that the installation was carried out as tested. For example, at Promat we carry out our own official fire tests, and the installation method can be found in the resulting classification report. The installer has to show that they followed the classification report, but they can also use photographs to demonstrate that the work was indeed carried out that way. This helps show what is behind a finished wall or cladding. So installation companies need to draw on their experience and document their work to avoid disputes later on.
Regulations versus practice
Vincent Vancaeyzeele Ultimately, it all comes down to the rules, technical requirements and standards being used. Where would you say regulations are ahead of, or lagging behind, practice?
Bart Tastenoye I think the regulations themselves are sound at the moment. I do not get the impression that they want to keep making them stricter just for the sake of it. Nor do I get the impression that they disregard technical feasibility. They do not always align, and sometimes there is a discrepancy.
Vincent Vancaeyzeele Can you give an example?
Bart Tastenoye As I said earlier, there are buildings where a high fire-resistance classification is required for one function, while a lower classification applies to another function or part of the building. Take a warehouse, for example. As long as the gate is open, everyone can get out very quickly. That is less straightforward in other settings. Warehouses also have sprinkler systems at ceiling level, to extinguish everything at once. But if you look at hospital corridors, for example, the people there are not mobile, so they need to be able to get down quickly from the fourth or fifth floor, and so on.
Specifications, inspectors and collaboration
Bart Tastenoye I think the general specifications should focus a little more on what makes practical sense, rather than saying: we are going to do everything this way. Or: we are going to insist that everything has at least this classification and is built to this standard. Because that makes a building expensive, firstly, and secondly, it leaves installers wondering: why on earth do we have to do it like this? That is why I think collaboration between the installation company and the inspector is so important, particularly when a specialist inspector is responsible for checking these things. In practice, I think they should work together more, which happens less often at the moment. I do not get the impression that many installers are keen to call these people while they are carrying out the installation. If something has been specified incorrectly, that is not the right way to go about it, in my view.
Bart Tastenoye If you work with someone who is well-informed, you can already plan at the costing stage to take a different route with your cable, for example, to avoid a particular zone and prevent any clashes, rather than having to resolve the clash afterwards by running an extra cable or rerouting it entirely. These may seem like details, but sometimes they are not. If we are talking about a few kilometres of cable, you will certainly feel the cost of putting things right after the inspector has visited and the problems have to be rectified.
Regulations, the fire service and specialisation
Vincent Vancaeyzeele Bert, do you think they are open to making certain decisions or even recommendations in advance of the inspection?
Bert Van Vaerenbergh In our market, there is not always a testing or certification body involved. But I do think we can say that Belgium has sound regulations. The rules have to be followed. Of course, it is not easy for a small installer to work through the Royal Decree and interpret the regulations correctly. But the fire service also sets certain requirements as part of the permit process, whatever the situation. And fire services, or their fire prevention advisers, are also more accessible when it comes to seeking advice on practical implementation. Installers, of course, need to specialise in this area. So I think specialisation is key here.
Bert Van Vaerenbergh But it is also partly our job as a supplier, tester and developer of fire-safe systems to support installers in finding the right solution and installing it correctly. This is especially important for larger, more complex projects. The architectural and building services engineering firms are responsible for determining where each penetration and each service should go. It then takes collaboration between the different parties to arrive at the right application. And the system needs to be documented in advance so that the right solution can be selected. We often see this in older buildings when the client asks us to carry out a walk-through and check whether the work has been done properly: we regularly come across things that are simply unacceptable. If necessary, the work has to be done again. That happens more than once, of course.
New technologies and the role of the fire service
Vincent Vancaeyzeele The fire service has been mentioned. The feedback we get from the trade federation is that the rules are clear for existing technologies. But when it comes to new technologies, such as EV charging infrastructure in underground car parks, or concerns from the US market about the impact of solar panels, we see that the fire service is sometimes still working out what needs to be done. There are large fire service zones and small ones, and opinions differ. You cannot install sprinklers every two metres everywhere. In large cities, some water supply requirements or storage requirements can also be impossible to meet. What are you seeing from the fire service? Is it working well? Can they provide support?
Bert Van Vaerenbergh Yes, that is right. The fire service provides advice. But in principle, that advice is based on the regulations, on the Royal Decree. So the fire service cannot simply impose requirements arbitrarily. It can make a suggestion, for example, about sprinkler systems in underground car parks. But that advice should be properly substantiated with reference to the Royal Decree. And yes, there is often some uncertainty about what is actually needed. That applies today to electric vehicles and charging infrastructure. But I thought the regulations in that area had become clear too. In any case, the exact requirements will come to the fore more and more in the coming years.
Innovations in fire detection and extinguishing systems
Vincent Vancaeyzeele Yes, perhaps we can talk about innovations again. New systems are entering the market, for example fire detection systems that do not use a thermal detector, but instead use a camera to detect smoke and fire. What is your view of these systems? What possibilities do they offer, and are you investing in them?
Bart Tastenoye Of course, all technical systems need connections. We are involved in junction boxes, control cabinets and so on. They will be used wherever new technologies are introduced. Various technologies are indeed being developed to prevent fires and contain them once they have started, improving safety in buildings. They are certainly coming onto the market. Even drones are being tested for use as firefighting drones. Those are the kinds of things that make you wonder: how did they come up with that? But they are working on all of it. It is excellent, because it means that places that are very difficult to reach could, in principle, be reached quickly. The same goes for extinguishing systems. We have already talked about sprinklers, but there are also CO2 systems, foam systems and so on, depending on what the building contains. All this equipment needs to be in place, installed correctly, fully operational and tested regularly.
Data centres, AI and automatic fire detection
Bart Tastenoye These days, we do a lot of work on data centre installations. That is a very different matter. It is not always about saving lives. The main aim is to save data. You want to avoid getting servers wet, or at least minimise the number that do, when there is a fire and it needs to be extinguished. AI will also make detection much faster. I think it will also become faster to relay the information and take structural action automatically through a system in the future. That means not having to wait for someone to give the go-ahead before taking action. No, in the longer term, you will no longer need someone to do that. It will essentially become a kind of self-guiding system that activates a number of measures as soon as something is detected.
Bart Tastenoye They will come into the picture at some point. And as far as I am concerned, they are still the leading experts when it comes to fire. Following the Royal Decree is essential. So is providing additional safety measures, depending on what you put in the building. And in my view, when it comes to people’s safety, you should never, ever limit the measures in place.
Compartmentation and renovation of existing buildings
Bart Tastenoye Data security matters in data centres, but there is also the risk of fire spreading in areas where many buildings stand close together. Your building may have been properly upgraded, but the one next door could go up in flames if a small fire spreads across, and you cannot always predict that. Compartmentation can also contain a fire if something does happen. This applies to every new building and every renovation of an old one. We have seen this in various disasters, including in London, among others. There are plenty of examples. All these buildings need to be reassessed, at the very least when they are renovated. We should not assume that renovation is solely about making a building look better. Safety measures simply need to be improved in every building that is renovated.
Fire safety in the existing building stock
Vincent Vancaeyzeele There are indeed many buildings that have been upgraded, particularly in terms of energy performance. In the 1990s and 2000s, we saw that this could sometimes create fire safety problems. Bert, what general advice would you give for the existing building stock, some of which needs attention? In terms of cost and implementation, people need to agree, but it also has to be safe. How should you approach this if you own a building, or if you are a local authority figure responsible for ensuring your residents’ safety?
Bert Van Vaerenbergh Yes, I think this is an area of concern in Belgium, and probably in other countries too. There is a huge number of older buildings, not so much houses as apartment blocks. Just look at the coast, for example. They are all blocks from the 1970s and 1980s. The regulations at the time were very different from those in force today. I am thinking, for example, of ventilation shafts and service risers in general, where there is a risk of flames and fire spreading across horizontal compartment boundaries.
Bringing older buildings up to current standards
Bert Van Vaerenbergh Inspections are carried out to bring these buildings into line with current regulations. So this usually only comes up when a minor problem occurs. At that point, the building will be required to comply fully with the newer regulations. But there is a lot of work to be done, and it really requires a study. Companies looking to get started need a thorough study. Specialist firms need to assess the situation and work with manufacturers or system suppliers to find a solution. This is certainly an area of concern. Modern technologies and digitalisation should help with this.
New building systems and new fire tests
Bert Van Vaerenbergh We work in active fire protection. We focus on solutions for passive fire protection. But we are seeing a shift towards different building systems, such as CLT and timber frame construction. Because these use different materials, they require new fire tests. The same electrical conduits and other services still have to pass through these materials. The process of developing solutions is important, and that is where we are focusing our efforts.
BIM and digitalisation on site
Vincent Vancaeyzeele I hear you talking about digitalisation. We as a federation are also investing heavily in BIM, mainly as an important tool for streamlining communication. It can also help us anticipate the small problems you encounter on site. As you say, we take photos, which need to be linked to a location and be easy to access. It can help, but I hardly ever see it mentioned in specifications. Why is that? Why is everyone going digital, but no specification actually requires it?
Bert Van Vaerenbergh Yes, that’s right. In Belgium, it isn’t necessary or compulsory. That is often the case in neighbouring countries, but we are seeing a trend, a shift towards digitalisation. Orange Button is a system that allows the installer, architect and main contractor to use BIM plans and design drawings to see easily, even on site, for example on an iPad, where each penetration needs to go. They can immediately indicate which type of penetration they have installed at that position. The information can be linked together. That means there is less chance of errors, which is ultimately the point, and it also makes the work easier to check. We are already seeing a trend among larger building services contractors, with growing use of, and interest in, these tools.
BIM among manufacturers and installers
Vincent Vancaeyzeele I see you nodding, Bart. Are you seeing that too?
Bart Tastenoye Yes, we are. Manufacturers, including us, are making as many of our products as possible available for digital use and for BIM. That means the resulting plan can be filtered and made as complete as possible, and increasingly so. Because BIM is used more in our neighbouring countries, many more brands now make their products available too, which is a good thing. On top of that, more and more installers, particularly the larger ones, are seeing the benefits of following a BIM-based approach. As my colleague says, you make far fewer mistakes in the first phase. That means you have fewer things to put right later, as I said earlier. Fixing those mistakes afterwards is, firstly, technically more difficult. Secondly, it probably costs money too. That is one of the weak points of our sector.
Bart Tastenoye Those three points mean that larger companies can ensure greater certainty by working with BIM from the outset. It may require a little more preparatory work and more hours from them, but when it comes to installation, things will be much easier and there will be far fewer mistakes, and so on.
Ask for advice to prevent mistakes
Vincent Vancaeyzeele What tip would you like to leave our listeners with? What else can be done on site to make things go better, faster and more efficiently?
Bert Van Vaerenbergh To avoid mistakes, my tip for installers is to contact us about penetrations, but also about compartment walls. Wherever there are fire-resistance requirements, we can always advise on finding a solution. We can provide practical support and advice to help prevent problems.
Cooperation between different installers
Vincent Vancaeyzeele We’ve had a fascinating conversation. I’ve asked a lot of questions. Is there anything else you’d like to bring up yourselves? Anything you’d say: Vincent, you’ve forgotten this?
Bart Tastenoye Yes, perhaps I’ll be the first to pick up on that. Cooperation between the installers of different systems is sometimes an area, especially on larger installations, where I think things could be better. If we used BIM more, everyone would have to incorporate their plans or sections of their installation into the same model. But we do see that some building services installers, sometimes the electrical contractors, sometimes the installers of solar panels, as you mentioned earlier, may be a different contractor. Nor are they always coordinated by a single company. As a result, some people, for example when installing fire-resistant cable support systems designed for a specified cable load in kilos, simply say: ‘Oh, look, here’s a cable tray.’
Additional cabling and load capacity
Bart Tastenoye I still need to add something for, say, 15 cameras or whatever. Those are exactly the things that cause problems later, because of course everything is calculated in advance, including what needs to go in and what doesn’t. If this were better coordinated at an earlier stage between all the different companies that need to install something, the cable tray could be made suitably heavy-duty to withstand additional cables being added. That wouldn’t be a problem. But if we are talking about a certain amount of additional cabling, that adds kilos per metre to the calculated load. The support structures may simply no longer be designed for it. You might think you have a circuit integrity system, but in reality you don’t, or it offers only limited assurance. My suggestion is that building services contractors should coordinate more closely with one another. They should check what cables still need to be installed, so they don’t get in one another’s way, and do the same for cable trays and so on, to avoid damaging the installation before it has even been commissioned.
Coordination within construction teams
Vincent Vancaeyzeele Yes, that will be a major challenge. I know that construction teams are being used more and more. Of course, I understand the installer’s position too. Solar panels on a roof are installed by a roofer and an electrical contractor. Ventilation is a completely different trade. Heating is another trade again, and at a different stage of the construction process. So I know exactly what challenge you’re describing. It’s enormous and won’t be resolved overnight. I should perhaps add a note of realism there. But we know what we need to work towards. Bert, over to you as well, I’m not sure.
Specialisation and choosing the right partner
Bert Van Vaerenbergh Building has become more intensive and more difficult. Regulations change, construction methods change, requirements differ and new systems are introduced. It is therefore difficult for installers to keep up with all these niche markets and systems. So here’s a tip: choose the right partner. Choose one who knows Belgian legislation and can offer the right advice and solutions. They should also specialise in one or more specific markets. That will help you avoid many problems.
Closing remarks
Vincent Vancaeyzeele Choose the right partner. I think that applies both in professional life and in private life. That’s one final tip for all our listeners who are on their way now. I can only thank you warmly, Bart and Bert, for this incredibly fascinating conversation. This is certainly a topic we’ll be hearing a lot more about, and one everyone will come across sooner or later. Many thanks.
Bert Van Vaerenbergh Thank you very much. Thank you for the opportunity. Thank you. Thanks.
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeFire safety in building services
- SubjectNews
- CompanySpelsberg Belgium
- CompanyPromat