The University Hospital Antwerp (UZA) has been a hive of activity in recent years. Ambitious new-build projects are preparing the hospital for the future. One of the major projects on the site was the construction of the so-called ‘Building J’, which will serve as a centre for clinical pharmacology and as a donor centre for the Red Cross Flanders. The building stands out for its forward-thinking choice of humidification system. DriSteem’s adiabatic system ensures energy-efficient and, above all, hygienic humidification.

Building J is located right in the heart of the UZA site, in the shadow of the majestic main building. At a later stage, it will be connected to the Emergency Department, which is due to be expanded in the near future. Although, strictly speaking, Building J is not a hospital building, and is therefore not subject to stringent hospital standards, its function and visitors naturally mean that it has certain things in common with a hospital. And hygiene is, of course, vital in a hospital.
Carefully considered air handling was therefore essential in Building J. Dirk Gestels, New-build Technical Services Project Manager at UZA: “All the air handling units on the site are equipped with humidification as standard. In the hospital’s existing buildings, we use the central steam network for this, and therefore the steam that is already available,” says Gestels. The situation was different in Building J, however. “It was decided early in the process that we would not use fossil fuels here. The HVAC system is therefore entirely electric, with a heat pump at its heart. This also means there is no steam production, so we had to find an alternative for humidification. The solution also had to meet some practical requirements. The available length of the humidification section was limited, for example, and immediate atomisation and absorption were essential.”

VDI 6022
Electric humidifiers were ruled out because these units require too much power. At the instigation of engineering consultancy BUREAU PARTNERS, ARCHITECTEN & INGENIEURS, low-pressure humidification was chosen, specifically adiabatic humidification. This technology happens to be DriSteem’s speciality. “With B-Eco, we offer an adiabatic humidification unit that uses hardly any electricity and fully meets the strictest hygiene requirements,” says Marc Briers, Managing Director of DriSteem Belgium. According to Briers, B-Eco’s VDI 6022 certification is further proof that the solution guarantees thoroughly hygienic humidification. “VDI 6022 is a German hygiene standard that specifies that everyone in a given space must be exposed only to perfectly hygienic air.” Dirk Gestels also says that this certification was an important factor in choosing B-Eco.
One hygiene advantage of the chosen system is that B-Eco guarantees hygienic air without adding any additional products. Other technologies, for example, require chemicals, biocides or heavy alloys to be added to kill pathogens. These additives are not needed with B-Eco, as it uses RO water,” he explains.
B-Eco also offers nothing but benefits in terms of energy efficiency. “The humidification process itself is extremely efficient because the air is preheated via the heat wheel. This provides heat efficiently for adiabatic humidification. What’s more, when you use steam, you always have to account for transmission and condensation losses. That is not an issue here,” says Marc Briers, who is also pleased with the excellent collaboration with Dirk Gestels and his colleague Dirk De Man, Head of Technical Services at UZA.

Precisely modulating control
B-Eco atomises the air at low pressure in combination with a re-evaporation pack. “We call this a two-stage hybrid operation,” says Briers. “It offers nothing but advantages, including a low air-side pressure drop and particularly precise modulation of the amount of water atomised into the airstream. This method allows the unit to be controlled with great precision. At UZA, the deviation is less than 1 per cent.”
“We are impressed by the precision of the solution provided by DriSteem,” says Dirk Gestels. The choice of B-Eco followed lengthy discussions with the contractor. “I also had to be convinced of its control capability. I thought steam could be controlled more effectively, but it soon became clear that this concern was unfounded. We can monitor the humidification system’s operation at any time via our building management system, and we can rest assured: B-Eco works as precisely as a Swiss watch. If we need humidification again in future in locations where steam is not available, we will certainly choose this adiabatic system again.”
Een zakelijke vraag aan Dristeem Belgium? Get in touch
Wie aan Gebouw J werkte
- engineering consultancyBUREAU PARTNERS: ARCHITECTEN & INGENIEURSIn this story
Keep following this
Get an email when a new story is published. No account needed.
- ProjectGebouw J
- ThemeHealthy air and summer comfort
- SubjectHVAC
- CompanyDristeem Belgium
- CompanyBUREAU PARTNERS – ARCHITECTEN & INGENIEURS