HVAC

Fresh Warehousing opts for a green cooling system from Daikin

Fresh Warehousing opts for a green cooling system from Daikin

Fresh Warehousing in Meer stores reefer cargo, such as bananas and other fruit, arriving at the ports of Antwerp, Rotterdam and Vlissingen. To preserve the fruit between its arrival in Belgium and its distribution across Europe, the company provides, among other things, storage space. A reliable cooling system is therefore essential. The bananas are stored at a maximum temperature of 14 degrees. In the summer of 2018, the company’s old system was due for replacement. After TWS Cool Service carried out a thorough assessment of the requirements and options, Fresh Warehousing opted for new Daikin chillers that are better for the environment, thanks both to their high energy efficiency and to the R1234ze refrigerant.

Refrigerant CO2 equivalent falls by 99%
Until recently, Fresh Warehousing cooled its fruit using two refrigeration plants with Bitzer compressors, supplemented by a separate refrigeration unit. Together, these systems contained more than 1,000 kilograms of refrigerant. The two new Daikin chillers, rated at 116 kW and 266 kW and equipped with inverter-driven single-screw compressors, use less than 100 kilograms of refrigerant between them.

The R1234ze refrigerant used in the new system is also far less harmful to the environment. It has a Global Warming Potential (GWP) of just seven. Replacing the old R130 refrigerant with R1234ze therefore reduces the potential CO2 equivalent by 1,863 tonnes, or 99%. CO2 equivalent is a unit of measurement used to express the warming potential of greenhouse gases, with CO2 as the reference gas. Energy consumption for cooling has also fallen: thanks to the system’s oversized capacity, it never has to run at full load, ensuring optimum efficiency at all times.

The new system represented a substantial investment for Fresh Warehousing, but one that was well worth making. “The fruit sector cannot ignore the climate issue. It is therefore something we take very seriously. To do our bit and send a positive message to our customers, we have made our new system as green as possible,” says Harry de Koning, President Advisory Board at Fresh Warehousing.

Confidence for the future
With its new cooling system, the company has opted for a long-term strategy. The system is not only environmentally sustainable, but the Daikin inverter chillers are also much more economical to run. The price of the old refrigerant had already been rising sharply for several years, making future costs difficult to predict. Daikin guarantees that the current R1234 ZE refrigerant will remain available for at least 15 years, with less risk of steep price increases.

Maintenance costs for the new Daikin system are also lower. Fresh Warehousing’s premises are usually packed with boxes of bananas. Technicians therefore had to manoeuvre between the boxes to carry out leak checks, making the task very time-consuming. “With these new chillers, leak tests are much easier to carry out, as they are only needed around the equipment installed outside the warehouse,” says Maarten Verbiest of TWS Cool service. “I believe the system will have paid for itself within three to four years, thanks to lower maintenance costs, the smaller quantity of refrigerant and the much higher efficiency of the new Daikin chiller,” he adds.

Nieuw in het assortiment bij Linum Europe is het Fieldpiece programma.

From old to new in a split second
Bananas, Fresh Warehousing’s core business, must never be stored in a space warmer than 14°C. At higher temperatures, the fruit starts to ripen. Bananas also generate heat as they ripen. In a storage space like this, where as many as 50 containers, or more than 1,000 tonnes of bananas, can be stored, that heat spreads like wildfire. “One banana sets off the next, and from that point the process can no longer be stopped. So we could not stop cooling the space at any point,” says Managing Director Wouter de Koning.

Keeping the temperature constant during the work presented a number of challenges. “We carried out the entire installation while the old chillers were still running. Once we were ready to switch over, the chillers had to start up in a split second. The installers managed to do that. The work took place in the middle of summer, so we started very early in the morning to ensure there was no risk of the warehouse being left without cooling in the full heat of the afternoon sun. Fortunately, everything went smoothly,” says Kris Mertens, Daikin’s project engineer.

Scope for expansion
To eliminate any risk of a refrigeration plant failure, an additional Daikin chiller was brought in during the work in case the 15-year-old system broke down. An extra chiller can also be connected to the outside of the new system in future. This prepares the company for unforeseen circumstances, such as a fault or extreme heat, as well as possible future expansion. “There are no concrete plans yet, but we may want to expand in future. The fact that TWS Cool Service and Daikin are already taking this into account will undoubtedly make the expansion process easier,” says Wouter de Koning.

Daikin installed two chillers:

Daikin chiller EWAH220TZ-XS B1
Daikin chiller EWAH270TZ-XS B1

Een zakelijke vraag aan Daikin Europe? Get in touch

Companies in this story

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectHVAC
  • CompanyDaikin Europe
Share this article

Follow on Installatie & Bouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.