Testing electrical (PV) installations is on the rise

When purchasing new equipment, it is best to check beforehand whether the measuring instrument has the functions for the measurements you want to carry out in the coming years.
When purchasing new equipment, it is best to check beforehand whether the measuring instrument has the functions for the measurements you want to carry out in the coming years.

There are several reasons why testing is becoming increasingly important. Some PV installations are now 20 to 25 years old. IV curve measurements can be used to assess whether these installations are still profitable and may need replacing. At the same time, the PV market has grown explosively in recent years, attracting unqualified parties with limited expertise. This can have serious consequences for electrical safety.

Is testing compulsory?

It would be good practice to carry out polarity and insulation resistance tests once a PV installation has been completed. These tests can reveal connection errors that could cause a fire. Such tests are not compulsory at present, but there is a real chance that requirements will be introduced in the future.

Periodic inspections

When completing an electrical installation, the installer must ensure that it complies with the AREI (General Regulations on Electrical Installations). At commissioning, it is advisable to carry out a number of tests to check that the PV installation is safe and working properly. The same test instrument could be used for periodic inspections to establish whether any changes have occurred and/or whether something is wrong. It is certainly worth rechecking the open-circuit voltage (Voc) and short-circuit current (Isc), preferably comparing them with the Standard Test Conditions (STC) in the datasheet. Periodic inspections would benefit the safety, profitability and service life of the panels.

However, it is important to bear in mind that PV installations cannot be easily de-energised. A dedicated insulation resistance tester must be used for this purpose. This functionality is not available on a standard resistance meter.

Testing charging points: check and think ahead

When it comes to testing, it is best to check carefully before buying whether the instrument is suitable for the tests you intend to carry out. For example, you can use a standard installation tester to test a charging point, provided you use the correct adapter. But take care: not all installation testers have a 6 mA residual current device test function, even though charging points often use a 6 mA residual current device. So, before buying new equipment, it is best to check whether the test instrument has the functions you will need for the tests you plan to carry out in the coming years.

Question about this story? Ask your question

Keep following this

Get an email when a new story is published. No account needed.

What you follow
  • SubjectElektroTech
Share this article

Follow on Installatie & Bouw Vlaanderen

Follow

Follow a project or company and you’ll receive an email whenever a new story appears. Follow a theme or topic and you’ll receive a weekly roundup. No account or password needed: every email includes a link to what you follow.