The Pen | Isabelle Verhaert, Project Developer at Revive

A heat network for Minerve
Revive is a project developer that delivers new residential projects in urban areas, close to public transport and amenities. We usually start with a contaminated industrial site facing complex demolition and remediation challenges. This is also the case for Minerve, the mixed-use residential neighbourhood we are currently building on the boundary between Mortsel, Edegem and Wilrijk. Minerve will become a green neighbourhood with around 300 homes and related facilities. A key part of the project is the construction of a heat network. It has been a project with many challenges along the way.
The site itself has a very rich history. From 1903 onwards, the site was used in turn by the Minerva car factory, Imperia and aircraft manufacturer Erla, during the Second World War. From 1953, it became Agfa-Gevaert’s fourth site. Today, the focus of its production has shifted from analogue photography to medical imaging. Reorganisation freed up parts of the site for redevelopment, including Minerve and Zilverkwartier. Aside from this change in production, Agfa-Gevaert remains a very large traditional industrial site, with its own heat networks operating at different temperatures. It already filters its own water and recovers waste heat for reuse at several locations across the site.
It therefore made sense that the idea of using Agfa-Gevaert’s waste heat to heat all the new developments around the site emerged at an early stage. The technical feasibility of such a heat network was investigated. Although the findings were positive, it later became clear that the proposals could not be implemented. Kelvin Solutions, which had been commissioned to assess the financial feasibility and establish the legal framework, had to carry out the entire technical study again. Agfa-Gevaert played a crucial role, first by granting full access to its site, and also by sharing its employees’ knowledge of its installations, efficiency improvements and waste heat.
Once the heat network had proved technically and financially feasible, all parties went back to the drawing board with their own figures. Feasibility was reassessed several times as part of a negotiation process, with the project seeming less and less viable each time. During this process, we also got to know our final supplier and distributor: Warmte Verzilverd. It is a company jointly owned by Ecopower, Zuidtrant and Kelvin Solutions.
This is the second heat network in Belgium where a private company supplies heat to a residential neighbourhood, and we covered all the back-up scenarios in the legal framework agreement. Strangely, the government was absent from these discussions, and I often wondered what the real incentives were for companies such as Agfa-Gevaert and Revive to keep negotiating through these difficult discussions. Throughout the negotiations, all parties around the table shared the view that, alongside creating economic value for our companies, we also have an important responsibility to generate social value. Agfa-Gevaert and Minerve are a stone’s throw from each other: one site has surplus heat, while a new development needs heat. If we could not make this “simple” project work, every heat network in a dense urban area would be doomed, let alone other climate challenges.
Right at the end of the process, we did eventually receive a subsidy from the Flemish Government. This support is certainly welcome and also convinced the last sceptics of the value of the project. But if a subsidy is truly intended to act as a catalyst for innovative projects, it will have to be awarded in a very different way. Projects the government genuinely wants to see happen should receive support upfront, not afterwards.
Collaborating on an innovative project that is new to the parties involved requires a great deal of trust. This trust grew over the course of the process we have been through over the past 2 years, but it still depends far too much on the people sitting around the table at any given time. If new sustainable projects are to be delivered at a faster pace, we will have to consider a radically different process and better incentives.