Internal insulation without the risks: how to get it right, according to Buildwise

Internal insulation of façades is the logical choice for many renovation projects, but it is also the subject that gives rise to the most uncertainty. In this episode, Timo De Mets, R&D Expert at Buildwise, joins the discussion.
The aim of the podcast? To dispel that uncertainty with a clear message: internal insulation is perfectly feasible. The key? Take a structured approach.
Why internal insulation matters so much today
De Mets puts it straight into the context of the wider renovation challenge: “If we want to make our buildings more energy-efficient and prepare them for the future, we need to look at the entire building envelope. Upgrading roofs and windows is usually straightforward. Façades, however, are more complex: they cover a large area, have a major impact and often come with constraints.”
There are essentially three techniques for insulating façades:
Cavity wall insulation
This involves filling the existing cavity with insulation material. It is relatively simple and affordable, but limited by the available cavity width. What’s more, many older homes do not have cavity walls.
External insulation
Here, insulation is installed on the outside of the façade, usually finished with render or cladding. Technically, this is often the most robust solution, but it changes the appearance of the façade and is not always permitted or desirable. Listed buildings and limited plot space are examples.
Internal insulation
Here, insulation is installed on the inside of the façade. This preserves the appearance of the façade, but requires greater attention to building physics because it changes how the existing wall dries out.
“Internal insulation is therefore not an exception, but often a necessity,” says De Mets. “And yet, in practice, there is still a great deal of hesitation.”
Where does the concern come from?
Hesitation about internal insulation is mainly due to moisture. And that concern is justified, De Mets explains: “When you insulate from the inside, it changes how the existing wall dries out. The wall gets colder and takes longer to dry. Rainwater, which used to be relatively harmless because it could dry out quickly, can remain in the wall for longer. This increases the risk of problems.”
A classic example is the ends of timber joists embedded in the wall. Before insulation, they were in a relatively dry, warmer part of the wall. After internal insulation, they may end up in a colder, damper zone. Without the right precautions, this can lead to deterioration or timber rot.
“But,” De Mets stresses, “that does not mean internal insulation inevitably causes problems. It means you need to approach it thoughtfully.”


Technical Information Note 300: a structured approach, not guesswork
That is precisely why Buildwise is publishing the new Technical Information Note (TV) 300. It provides clear guidance for anyone looking to apply internal insulation safely and on a sound basis. The approach consists of three steps.
1. Thorough preliminary investigation
Internal insulation starts not with insulating, but with analysis. Are there existing moisture problems? What condition is the masonry in? Are there timber or metal elements built into the façade? What is its orientation, and how high is the exposure to driving rain?
The aim is not to avoid risks by doing nothing, but to assess them correctly and make them manageable.
2. System selection and design
There is no universally ‘best’ system. The right choice depends on the project’s priorities: acoustics, fire safety, environmental impact, loss of internal space, and so on.
Correct design is also important. More insulation is not automatically better. Excessive insulation thickness can further slow the wall’s drying process and thus increase the risk. TV 300 therefore provides practical guidelines and tables for determining a safe maximum insulation thickness for each situation.
It is not just about choosing a material, but about the complete system: fixings, airtightness, any vapour barriers and the internal finish.
3. Attention to construction details
Even the best system will fail if poorly installed. Junctions with floors, internal walls and window openings are crucial. If these thermal bridges are not dealt with correctly, the energy savings may be only a fraction of what is expected. In the worst case, mould problems can arise.
Internal insulation therefore calls for precision, both in the design and on site.
A fully fledged renovation tool
The podcast’s core message is clear: internal insulation is not a last resort. When applied correctly, it is a fully fledged tool within a wider renovation strategy.
With TV 300, Buildwise aims above all to give professionals confidence. Those who understand the building physics, carry out the right preliminary analyses and pay attention to design and details can apply internal insulation safely and sustainably. No guesswork, then, but decisions based on sound evidence.
Keep following this
Get an email when a new story is published. No account needed.
- SubjectNews