Fluvius renews key gas supply infrastructure for Ghent city centre

Fluvius is currently carrying out major works on the natural gas network along Afrikalaan in Ghent. The Flemish network operator is replacing five ageing gas valves and installing new pipes, among other things to ensure that two key supply pipelines serving Ghent city centre can be switched between. The project is part of general maintenance work on Ghent’s natural gas network. The works will continue until mid-October.
At two locations near the Decathlon store on Afrikalaan, Fluvius is carrying out major renewal work on Ghent’s natural gas network. Five huge gas valves, around 40 years old, were difficult to operate. They are now being replaced with modern units. Valves are devices that shut off the gas supply in a pipe.

Two of these valves are beneath the Decathlon car park, and the other three beneath the junction of Afrikalaan and Aziëstraat. These valves are about 2 metres tall, have a diameter of half a metre (or slightly less, depending on the type) and weigh around 2 tonnes (2 000 kg).
New valve manifold
Fluvius is also installing a new valve manifold beneath the junction of Afrikalaan and Aziëstraat. This is an additional connecting structure between parallel pipelines. Part of a pipeline often has to be shut off during renewal and repair work. A flexible valve manifold makes it possible to switch the gas supply easily and safely, so customers are not affected by the work.

Gas network renewal
The work on Afrikalaan is part of a general Fluvius maintenance project to renew the natural gas network in the city of Artevelde. The area around Muide-Meulestede-Afrikalaan plays an important role in this. The receiving station on Rigakaai supplies several gas pipelines that serve numerous districts in Ghent.
Two of these key gas supply ‘arteries’ run parallel to each other for several metres beneath the junction of Afrikalaan and Aziëstraat, carrying gas to the centre of Ghent. This made the location ideal for installing a new valve manifold connecting the two pipelines.
Overall project in three phases
Fluvius has already carried out two other major renewal operations in the district. Some time ago, new valves were installed on another supply pipeline behind Decathlon, which supplies gas to Mariakerke. And a few years ago, Fluvius renewed the ‘sinker’ at Muidebrug. This is a pipeline laid along the bed of a river, canal or other waterway.

Safe and reliable
The renewal work on Afrikalaan is currently the final stage of the overall project Fluvius launched to optimise the operation of the natural gas network. As society transitions towards climate neutrality by 2050, the Flemish network operator is responsible for continuing to ensure the reliability and safety of our gas pipelines.